Risk Assessment vs Method Statement (RAMS): Key Differences
compliance

Risk Assessment vs Method Statement (RAMS): Key Differences

SiteChief Team
13 August 2026
7 min read

A risk assessment identifies what could cause harm and how likely it is. A method statement sets out, step by step, how the work will actually be done safely. The first is about the hazards; the second is about the method. Together they are usually called RAMS.

If you have ever been asked for "your RAMS" before starting on site and wondered whether that meant one document or two, you are in good company. The two are related, frequently bundled, and routinely confused — including by people who produce them every week. The distinction matters, because only one of them is explicitly required by law.

Risk assessment vs method statement at a glance

Risk assessment Method statement Question it answersWhat could go wrong, and how bad could it be?How exactly will we carry out this task safely? FocusHazards, who might be harmed, likelihood and severity, control measuresSequence of work, equipment, people, permits, emergency arrangements Legal status (UK)Explicitly required by the Management of Health and Safety at Work Regulations 1999Not named in legislation, but the practical way of demonstrating a safe system of work Typical formatMatrix or table scoring each hazard before and after controlsNumbered, chronological narrative of the job AudienceAssessors, managers, auditors, enforcing authoritiesThe crew doing the work, and the client or principal contractor Comes first?Yes — it informs the methodNo — it is written around the controls the assessment identified

What is a risk assessment?

A risk assessment is a systematic examination of what, in your work, could cause harm to people — so you can weigh up whether you have taken enough precautions or should do more.

In Great Britain the duty comes from regulation 3 of the Management of Health and Safety at Work Regulations 1999, which requires every employer to make a "suitable and sufficient" assessment of the risks to employees and to anyone else affected by the work. If you employ five or more people, you must record the significant findings.

The HSE's familiar five steps still describe the process well: identify the hazards, decide who might be harmed and how, evaluate the risks and decide on precautions, record your findings and implement them, then review and update. Most organisations score each hazard on a matrix — commonly 5x5 — both before and after controls are applied, which makes it obvious where the residual risk is still unacceptable.

Crucially, a risk assessment does not tell anyone how to do the job. It tells you what you are up against.

What is a method statement?

A method statement is a written description of how a specific task will be carried out safely, from start to finish. It takes the control measures your risk assessment identified and turns them into practical instructions the crew can follow.

A useful method statement usually covers the scope of work and location, the sequence of operations in order, the plant, tools and materials involved, who is doing what and what competence or training they need, the PPE required, any permits such as hot works or confined space entry, arrangements for others affected nearby, and what to do in an emergency.

No UK regulation says "you must produce a method statement" in those words. What the law requires is a safe system of work — under the Health and Safety at Work etc. Act 1974 and, on construction projects, the Construction (Design and Management) Regulations 2015. The method statement is simply how that safe system is written down and communicated. That is why principal contractors ask for one before letting you on site.

So what does RAMS mean?

RAMS stands for Risk Assessment and Method Statement — the two documents supplied together as a package. It is a convention of practice rather than a legal term. When a client asks for RAMS, they want to see both that you understand the hazards and that you have a credible plan for controlling them.

Read in that order, the pair tells a complete story: here is what could hurt someone, and here is exactly how we will stop it happening.

Is a method statement the same as an SOP?

Not quite, though the two overlap. SOP stands for Standard Operating Procedure: a repeatable instruction for a routine activity, often written primarily for quality, consistency or efficiency, and typically reused unchanged across many jobs.

A method statement is narrower and more situational. It is written for a particular task in a particular place at a particular time, and it exists specifically to control the risks that task presents. Replacing a pump in your own workshop might be covered by an SOP; replacing the same pump nine metres up on a live site with other trades working below needs a method statement.

In practice many organisations keep a library of SOPs and adapt them into task-specific method statements when the setting demands it.

Do you always need both?

You always need the risk assessment. It is a legal duty, and it applies to every employer regardless of sector or size.

You need a method statement when the work is complex, high risk, non-routine, or carried out somewhere you do not control. In practical terms, produce one when the task involves work at height, confined spaces, hot works, excavation, lifting operations, live electrical work, asbestos, or demolition — and whenever a client or principal contractor asks for RAMS as a condition of access.

Straightforward, low-risk, familiar work is usually adequately covered by the risk assessment alone. Writing a method statement for changing a lightbulb helps nobody, and the paperwork nobody reads is a genuine hazard in itself.

Four mistakes worth avoiding

  • Writing the method statement first. If the method was not derived from the assessed risks, the controls in it are guesswork.

  • Generic copy-paste. A template with the site name changed will not survive contact with an inspector, or with the actual site.

  • Never reviewing them. Both documents should be revisited when the work, the people, the equipment or the location changes — not filed and forgotten.

  • Leaving them in a drawer. A method statement the crew has not read and signed is not a safe system of work; it is a document about one.

Managing RAMS without the paperwork spiral

The administrative burden is what breaks most RAMS processes. Assessments live in one folder and method statements in another, versions diverge, and nobody can prove who signed what.

SiteChief keeps them linked. Risk assessments are built on a 5x5 matrix with a hazard library and automatic review reminders, and method statements are generated from the controls those assessments identify — so the method always reflects the current assessment. Crews acknowledge them on mobile, and every version and signature is timestamped for when a client or the HSE asks.

If your work involves permits, the same records feed straight into permit to work, so the permit, the assessment and the method all reference one another.

The short version

The risk assessment is your analysis; the method statement is your plan. One is a legal duty in its own right, the other is how you prove the work will be done safely. Get the assessment right first, build the method from it, keep both current — and make sure the people doing the work have actually read them.

FAQs

Which comes first, the risk assessment or the method statement? 

Ans: The risk assessment comes first. It identifies hazards and controls, which the method statement then turns into a clear, step-by-step safe system of work. 

Are method statements a legal requirement in the UK? 

Ans: Not by name. However, the Management of Health and Safety at Work Regulations 1999 require risk assessments and controls, and method statements are the standard way to record them. 

Who should write a method statement? 

Ans: A competent person who understands the task, ideally with input from those doing the work. It should reflect real site conditions and be approved before work starts. 

How often should RAMS be reviewed? 

Ans: There is no fixed legal interval. Review them when work, site conditions, people or equipment change, after incidents or near misses, and at regular points set by company policy. 

Can one method statement cover several tasks? 

Ans: Only if the tasks are closely related and share the same hazards, controls and conditions. Otherwise, use separate method statements so task-specific risks are not missed.