How to Prepare a Construction Phase Plan

A practical guide for principal contractors under CDM 2015

12 min read Updated 4 October 2026 CDM 2015 reg 12 CDM 2015 reg 4 CDM 2015 Schedule 3 BCMS 2013 Part 8

Key takeaways

  • ยทCDM 2015 reg 12 requires the principal contractor to prepare a construction phase plan before construction work begins โ€” not after.
  • ยทThe plan does not need to be a lengthy document on day one โ€” it must be suitable at the start and developed as the project progresses.
  • ยทSchedule 3 of CDM 2015 specifies what the plan must address: project description, management arrangements, emergency procedures, welfare, and site-specific risks.
  • ยทThe plan must be kept up to date throughout the project โ€” it is a live document, not a box-ticking exercise at the start.
  • ยทIn Ireland, the Safety and Health Plan (BCMS 2013 Part 8) is the equivalent document, prepared by the Project Supervisor Construction Stage (PSCS).

What is a construction phase plan?

The construction phase plan (CPP) is the site-specific health and safety management document required under CDM 2015 reg 12. It is prepared by the principal contractor (or contractor, for single-contractor projects) and must be in place before construction work begins. It describes how health and safety will be managed on the project โ€” the arrangements, the site rules, the emergency procedures, and the specific risk controls for the work being undertaken.

The plan is not a static document. CDM 2015 reg 12(3) requires the principal contractor to develop and implement the plan as the project progresses. This means the level of detail at the start is necessarily limited โ€” it reflects what is known at that point โ€” but it must be kept current as the work develops, as new subcontractors come on site, and as the risk profile changes through the project stages.

The CPP sits alongside two other CDM documents: the pre-construction information (provided to the principal contractor by the client before work starts) and the health and safety file (compiled during the project and handed to the client at completion). The CPP uses the pre-construction information as its starting point and is the primary day-to-day site safety management reference.

๐Ÿ‡ฌ๐Ÿ‡งGreat Britain
CDM 2015 reg 12

Requires the principal contractor to plan, manage, monitor and coordinate health and safety during the construction phase. Before the construction phase begins, the principal contractor must prepare a construction phase plan. The plan must be kept up to date and must be made available to relevant parties.

CDM 2015 Schedule 3

Sets out the matters to be addressed in the construction phase plan: a description of the project; the management arrangements (site rules, induction procedure, emergency arrangements, welfare); the approach to managing specific risks; and the timing of site handover.

๐Ÿ‡ฎ๐Ÿ‡ชIreland
BCMS 2013 Part 8

Requires the Project Supervisor Construction Stage (PSCS) to prepare a Safety and Health Plan before construction begins. The plan must address the same core areas as the GB CPP. The PSCS is notifiable to the HSA for projects exceeding certain thresholds.

How to prepare a construction phase plan

1

Review the pre-construction information

Before drafting the CPP, obtain and read the pre-construction information (PCI) provided by the client (CDM 2015 reg 4(4)). The PCI is the client's compilation of information about the site and project that could affect health and safety during construction. It typically includes: existing services, known ground conditions and contamination, asbestos surveys and registers, the design risk register, and any site-specific rules or restrictions.

The PCI is the foundation of your CPP. Any site-specific risks identified in the PCI must be reflected in the CPP's risk controls. If the PCI is incomplete or unclear, raise this with the client and the principal designer before construction starts โ€” you cannot plan effectively for risks you have not been told about.

2

Draft the plan before work starts on site

The CPP must be in place before construction work begins (CDM 2015 reg 12(1)). At this stage, the plan needs to address the Schedule 3 matters at a level appropriate to what is known at project start. This includes: a clear description of the project and the construction phase; the management structure (who is the principal contractor, who are the site managers and supervisors, what is the chain of command for safety decisions); site rules (hours of work, vehicle and pedestrian segregation, PPE requirements, restricted areas); emergency arrangements (assembly point, nearest hospital with A&E, emergency contact numbers, fire warden arrangements); welfare facilities arrangements; and a summary of the known significant risks and how they will be controlled.

A common error is to create a detailed CPP for all phases of the project at the outset. This is unnecessary and often counterproductive โ€” it fills the document with speculative content that becomes inaccurate as the project evolves. Start with what you know; develop the plan as you proceed.

3

Address Schedule 3 matters specifically

CDM 2015 Schedule 3 lists the matters the plan must address. Work through each one explicitly: the project description (scope, programme, and key milestones); management arrangements including induction procedure, site rules, and communication arrangements; the arrangements for managing specific site risks (working at height, excavations, hazardous substances, services, temporary structures, fire, and plant management); welfare facility arrangements; and the arrangements for coordinating subcontractors.

For each significant risk, the plan should cross-reference the method statements and risk assessments that address it. The CPP does not need to contain all risk assessments in full โ€” it should reference them and confirm they exist. However, it must demonstrate that each significant risk has been addressed by specific controls, not just acknowledged.

4

Brief the workforce and subcontractors

The CPP must be communicated to all those who need it. CDM 2015 reg 12(7) requires the principal contractor to ensure every worker receives suitable induction before starting work on site. The induction must cover the key elements of the CPP: site rules, emergency procedures, welfare locations, known significant risks, and reporting arrangements.

For subcontractors, the principal contractor must communicate the site rules and any relevant CPP provisions before the subcontractor starts work on site. The subcontractor's own method statements and risk assessments must align with the CPP. Where they do not, the principal contractor must resolve the inconsistency before work starts.

5

Keep the plan live throughout the project

The CPP must be kept up to date as the project progresses (CDM 2015 reg 12(3)). This means reviewing and updating the plan when: new subcontractors come on site; the scope or programme changes; a new significant risk emerges; an incident or near miss occurs; a specific risk phase (e.g. structural steelwork, deep excavations, asbestos removal) begins; or the emergency arrangements change.

Date-stamp every review and update. Keep a version history so that earlier versions can be retrieved if needed. The HSE or a court may want to see the plan as it existed at the time of an incident โ€” having a clear version history demonstrates active management rather than a plan that was written at the start and forgotten.

6

Hand over the health and safety file at project completion

The CPP is not the same as the health and safety file (HSF), but it contributes to it. The HSF is the document handed to the client at project completion, containing the information needed for future construction, maintenance or demolition work on the structure. The principal contractor contributes information to the HSF throughout the project, and the CPP may provide a useful source for the management and emergency arrangements sections.

Ensure the HSF is compiled and handed to the client before the construction phase is formally closed. The client has duties under CDM 2015 reg 4(5) to make the HSF available for any future project involving the structure.

Construction phase plan checklist

  • Pre-construction information reviewed before CPP drafted
  • Plan in place before construction work starts on site
  • Project description and programme included
  • Management structure (names and roles) documented
  • Site rules documented and signed off
  • Emergency arrangements: assembly point, hospital, contact numbers
  • Welfare facilities documented (toilets, washing, rest area, drinking water)
  • Significant risks identified with specific controls referenced
  • Method statements and RAs cross-referenced in the plan
  • Induction procedure documented and records kept
  • Subcontractor notification and briefing process in place
  • Plan dated and version-controlled
  • Review process established (triggers: incidents, new phases, new contractors)
  • HSF compilation process in place

Common mistakes to avoid

Starting construction before the plan exists

CDM 2015 reg 12(1) requires the plan to be in place before construction begins. Starting without it is a criminal offence and will likely result in a prohibition notice.

Using a template plan without site-specific content

A generic template CPP that does not address the specific hazards of the project (ground conditions, existing services, adjacent land use, specific work activities) is not a compliant plan under CDM 2015.

Never updating the plan during the project

CDM 2015 reg 12(3) requires the plan to be developed as the project progresses. A plan last updated at project start is unlikely to remain suitable and sufficient as significant risk phases (excavations, structural work, fit-out) commence.

Confusing the CPP with the health and safety file

The CPP manages health and safety during construction. The HSF records information for future maintenance and construction work. Both are required; neither substitutes for the other.

Not including welfare facility details

CDM 2015 Schedule 2 specifies minimum welfare facilities for construction sites. The CPP must address these. An HSE inspector will look for this specifically.

GB and Ireland: key differences

๐Ÿ‡ฌ๐Ÿ‡งGreat Britain

CDM 2015 reg 12. The principal contractor prepares the CPP. For single-contractor projects, the contractor prepares it. HSE inspectors regularly review CPPs during site inspections. The CPP is not required to be submitted to the HSE, but must be available on request.

๐Ÿ‡ฎ๐Ÿ‡ชIreland

BCMS 2013 Part 8. The PSCS (Project Supervisor Construction Stage) prepares the Safety and Health Plan. The HSA must be notified of projects exceeding 500 person-days or 30 working days with more than 20 simultaneous workers. The PSCS role broadly corresponds to the GB principal contractor.

๐Ÿ‡บ๐Ÿ‡ธUnited States

OSHA does not require a single equivalent document. Safety and health programmes for construction are required under 29 CFR 1926.20, and site-specific safety plans are required for some work types (excavations, scaffolding, steel erection). Many contractors voluntarily produce a project safety plan equivalent to the CPP.

Frequently asked questions

Ready to Join Us?

Start your journey towards simpler, more effective health and safety management today.

30-day free trial ยท Cancel anytime

We use cookies. Essential ones are on. Optional ones need your OK.