Site diary

A contemporaneous written record of construction activities, significant events, weather conditions, visitors, instructions given and work carried out on a construction site each day. Forms part of the health and safety documentation required on notifiable projects and provides evidence in the event of a dispute or incident.

By jurisdiction

🇬🇧

UK HSE

“site diary”Close equivalent

Not explicitly required by CDM 2015 as a separate document, but the duty to maintain the construction phase plan (regulation 12) and to keep records of inspections (Work at Height Regulations 2005, Schedule 7) creates a body of contemporaneous records that together constitute a site diary. HSE guidance and industry practice treat a daily site diary as essential records of the construction phase.

Jurisdiction note: A site diary is a matter of good practice and contractual obligation rather than a direct statutory requirement. It supports compliance with CDM and WAHR record-keeping duties.
RegulatoryConstruction (Design and Management) Regulations 2015, regulation 12; Work at Height Regulations 2005, Schedule 7Source
🇮🇪

Irish HSA

“site diary”Close equivalent

Not explicitly required by the Construction Regulations 2013 as a standalone document, but the duties of the PSCS to maintain the safety and health plan and inspection records create equivalent contemporaneous documentation. A site diary is expected as part of the safety management system for notifiable projects.

RegulatorySafety, Health and Welfare at Work (Construction) Regulations 2013 (SI 2013/291)Source
🇺🇸

US OSHA

“daily site log”No equivalent

No equivalent in this jurisdiction.

Jurisdiction note: OSHA has no specific site diary requirement. Construction safety records such as crane inspection logs, competent person reports and injury/illness records are required but there is no general site diary equivalent.
RegulatorySource

Practitioner note: Not explicitly required as a standalone document by CDM 2015, but the contemporaneous records required (construction phase plan updates, inspection records) effectively constitute one.

Ready to Join Us?

Start your journey towards simpler, more effective health and safety management today.

30-day free trial · Cancel anytime

We use cookies. Essential ones are on. Optional ones need your OK.