A temporary structure erected to provide a safe working platform at height. The erection, alteration and dismantling of scaffolds must be carried out by competent persons, and scaffolds must be inspected at defined intervals.

By jurisdiction

🇬🇧

UK HSE

“scaffold”Exact equivalent

The Work at Height Regulations 2005 require that scaffolds used as working platforms are inspected before use after assembly, after any event likely to have affected stability, and at regular intervals not exceeding seven days. TG20 (NASC technical guidance) defines industry standards for tube-and-fitting and system scaffolding in GB. Scaffold erectors must be competent.

RegulatoryWork at Height Regulations 2005 (SI 2005/735), regulation 12 and Schedule 7Source
🇮🇪

Irish HSA

“scaffold”Close equivalent

The Safety, Health and Welfare at Work (Construction) Regulations 2013 (SI 2013/291) require that scaffolds are erected, altered, and dismantled under the supervision of a competent person and inspected at prescribed intervals. The regulations implement the EU Temporary or Mobile Construction Sites Directive requirements for working at height.

Jurisdiction note: The Irish scaffold requirements are in the Construction Regulations. The inspection intervals and competence requirements are similar to GB but arise from a different instrument.
RegulatorySafety, Health and Welfare at Work (Construction) Regulations 2013 (SI 2013/291)Source
🇺🇸

US OSHA

“scaffold”Close equivalent

OSHA 29 CFR 1926 subpart L covers scaffolding in construction. Key provisions include load capacities, access, fall protection, and training. Scaffolds must be erected, moved, dismantled, or altered only under the supervision of a competent person. OSHA uses scaffold as a broad term covering many types (supported, suspended, aerial lifts).

Jurisdiction note: OSHA scaffold requirements are construction-specific (1926 subpart L) rather than covering all work at height. The fall protection requirements and inspection intervals differ from GB and Irish provisions.
Regulatory29 CFR 1926 subpart L; 29 CFR 1926.451Source

Practitioner note: Inspected before first use, then at intervals and after anything likely to affect stability. Check the handover tag before stepping on.

Ready to Join Us?

Start your journey towards simpler, more effective health and safety management today.

30-day free trial · Cancel anytime

We use cookies. Essential ones are on. Optional ones need your OK.