Sanitary and welfare provisions that must be made available on construction sites, including toilets, washing facilities, facilities for rest and eating, and facilities for changing and storing clothing.

By jurisdiction

🇬🇧

UK HSE

“construction site welfare facilities”Exact equivalent

Schedule 2 of CDM 2015 (SI 2015/51) sets minimum welfare requirements for construction sites. These include: adequate sanitary conveniences (one WC per 20 workers initially, reducing to one per 25); hand washing facilities; wholesome drinking water; rest rooms with seating and facilities to heat food; changing rooms and lockers where workers need to wear specialist clothing.

RegulatoryConstruction (Design and Management) Regulations 2015 (SI 2015/51), Schedule 2Source
🇮🇪

Irish HSA

“construction site welfare facilities”Close equivalent

The Safety, Health and Welfare at Work (Construction) Regulations 2013 (SI 2013/291) and the General Application Regulations 2007 set welfare requirements for construction sites. Requirements include toilets, hand washing, rest facilities and changing rooms appropriate to the number and gender of workers.

Jurisdiction note: Irish welfare requirements for construction sites are broadly equivalent to CDM 2015 Schedule 2 but specific ratios and requirements may differ.
RegulatorySafety, Health and Welfare at Work (Construction) Regulations 2013; General Application Regulations 2007Source
🇺🇸

US OSHA

“construction sanitation”Close equivalent

OSHA 29 CFR 1926.51 requires sanitation facilities on construction sites, including toilets (one for 20 or fewer workers; one toilet and one urinal for each 40 workers thereafter), washing facilities, and potable water. Food handling requirements also apply.

Jurisdiction note: OSHA 1926.51 ratios (1 toilet per 20 workers) match the CDM 2015 initial provision. Rest room and changing facility requirements are less prescriptive in OSHA than in CDM Schedule 2.
Regulatory29 CFR 1926.51Source

Practitioner note: Must be available from the start of the project, including on short-duration and transient sites. Provision is the principal contractor's responsibility.

Ready to Join Us?

Start your journey towards simpler, more effective health and safety management today.

30-day free trial · Cancel anytime

We use cookies. Essential ones are on. Optional ones need your OK.